Commissioner questions size of proposed incinerator

Subtitle:
Source: Gazette
Author: Charles Schelle
Article Type:
Date Published: 04/24/2008

Carroll County Commissioner Julia W. Gouge questions whether a proposed incinerator that Carroll is considering building with Frederick is too big. “We’re building a facility that is much larger than we need right now,” Gouge said. The proposal calls for the incinerator to be built in Frederick County, possibly near the Ballenger Creek-McKinney Wastewater Treatment Plant off Md. Route 85, with Carroll contributing $140 million to the $350 million project. The incinerator would handle 1,500 tons of trash per day, 600 tons of which would come from Carroll. However, Carroll only produces about 320 tons per day.